Meeting documents
- Meeting of Resources Overview Committee, Wednesday, 20th June, 2018 6.30 pm (Item 40.)
Minutes:
The Committee
agreed to consider the redevelopment of Chiltern Pools and adjacent community
facilities at item 5 of the agenda.
Members
received a report on the design, cost plan and business case for the
redevelopment of the Chiltern Pools project at supplementary agenda 1. It was
noted that a structural survey undertaken in 2015 which indicated that the
current centre had a lifespan until 2020; and addressing the structural issues
would have significant financial implications for the Council.
Two public consultations
undertaken by the Council found strong local support for a redevelopment of
Chiltern Pools, and for the bringing together of leisure and community
facilities. Two key areas of concern were raised during the consultation and
would look to be mitigated, namely the preservation of the barns and the need
for adequate parking on the site. It was reported that Amersham Town Council
had agreed to the disposal of land to the Council in return for the transfer of
the green at Woodside Close and edge of Chiltern Avenue. Further, that the
stage 2 designs were being finalised ahead of the detailed design phase.
A presentation
relating to the financial and business plan options appraisal was given to
Members by Managing Director of Knight, Kavanagh and Page, David McHendry. Members were advised that pursuing option 1 would
allow a higher net benefit to the Council. The centre would attract over
800,000 visits per annum with the health and fitness facility accounting for
40% of the total income. The facility mix would enable all identified needs to
be addressed with the Health and Fitness Centre sufficiently sized to
accommodate over 4,400 members.
The total
scheme including; library, community centre, nursery, swimming pools, sports
hall, dry diving, fitness studios and spa was projected to cost £34m. Further
key points from the business plan were highlighted:
·
The
base business plan was anticipated to generate £1.2m benefit to the Council
providing a £32m borrowing capacity, leaving a funding
gap of circa £2 million; assuming the Council would invest the current £200k
subsidy for its leisure management contract in the new development.
·
Applying a pricing
structure that recognises the investment in the facilities, (option 1) would
increase the financial return to the Council, and was anticipated to generate
£1.475m/annum, giving the Council a borrowing capacity of circa £38 million
over 45 years.
·
It
was expected that a ‘do nothing’ scenario would see an increase in the subsidy
from 200k to 700k per annum from 2021-2031 to undertake a backlog of
maintenance required to keep the facility safe and operational.
The Committee
raised the following key points:
·
Impact
on the usage and client base of the other centres as this could impact on
financial performance.
·
That
the risk be recognised of not being able to attract bidders for the management
contract of the new facility who would be prepared to take on the hoped for
income risk. The structural survey was important in this context.
·
Members
raised that testing with a lower level of investment,
the existing facility could be made more viable and the structural survey would
inform this.
·
Whether
the facility mix would attract the anticipated income as set out in the
options. A concern was expressed over the commercial approach to pricing.
Members noted that the size, scale and nature of the facilities offered would
allow the operator to attract larger and different catchment areas.
·
It
was recognised that the business plan accounted for an annualised programme of
investment over the full 45 years of the centre. However, a concern was raised
as to whether the centre would have a 45 year lifespan.
·
Members
enquired as to what consideration had been given to refurbishing the current
Chiltern Pools leisure centre.
·
It
was recognised that the current leisure centre accounted for a significant
amount of the Council’s CO2 emissions, and was highly inefficient in the use of
energy. The new leisure centre would be built with high sustainability
principles, reducing the impact on the environment and lowering future
operating costs.
·
Members
recognised that the community facilities would require to be subsidised as it
was unlikely that community organisations could
provide a commercial rent in return for lease.
·
Members
welcomed an option to incorporate social housing on the leisure and community
site.
·
That
the scale of investment and duration of contract meant that the Council needed
to carefully and thoroughly consider the issues and risks as it had done to
date.
Members expressed
thanks to David McHendry for an informative
presentation. The Chairman then advised the Committee of amendments to the
recommendations in the officer’s report.
The
RECOMMENDATIONS to Cabinet as per the officer’s report, and as amended were as
follows:
1. To note the findings of the current version of
the design proposals and business plan to re-provide a combined community and
leisure facility in Amersham.
2. To agree the facility mix incorporated in the
current design proposals and detailed in Appendix 1.
3. To delegate the decision to the Director of
Services to submit a detailed planning application for the proposed leisure and
community centre.
4. To delegate authority to the Director of
Services, to undertake a feasibility study of the development opportunities
offered by the release of the existing leisure and community sites (the
existing site) and subject to an outline business case, to submit a planning
application for that site at the
appropriate time.
5. To delegate authority to the Head of Environment
and Head of Legal to carry out due diligence to identify and take steps to
address any legal constraints for the proposed leisure and community centre
project.
6. To authorise the Head of Healthy Communities, in
consultation with the Support Services Portfolio Holder to draw down up to
£500,000 of funding from the Council reserves to enable an outline business
case, and planning application of the existing leisure and community sites (the
existing site) to be determined.
7. To authorise the Director of Services to agree
the maintenance arrangements for the land to be transferred to Amersham Town
Council.
8. To authorise the Director of Services to agree
the provision of replacement outdoor leisure facilities to be managed and owned
by Amersham Town Council following the transfer of the section of King George V
Playing Fields to be developed to the District Council.
Members
debated the recommendations. The Committee suggested delaying the submission of
a planning application for both the Chiltern life centre and existing community
and leisure sites until the feasibility study of the current site had been
considered by Members, as well as the results of the structural and mechanical
and electrical survey currently being undertaken. Following discussion, the
Committee RESOLVED
to
RECOMMEND to Cabinet: |
|
1.
To note the findings of the current version of the design proposals and
business plan to re-provide a combined community and leisure facility in
Amersham. |
|
2.
To agree the facility mix incorporated in the current design proposals and
detailed in Appendix 1. |
|
3.
To delegate the decision to the Director of Services to submit a detailed
planning application for the proposed leisure and community centre. |
|
4. To delegate authority to the
Director of Services, to undertake a feasibility study of the development
opportunities offered by the release of the existing leisure and community
sites (the existing site). |
|
5.
To delegate authority to the Head of Environment and Head of Legal to carry
out due diligence to identify and take steps to address any legal constraints
for the proposed leisure and community centre project. |
|
6.
To authorise the Head of Healthy Communities, in consultation with the
Support Services Portfolio Holder to draw down up to £500,000 of funding from
the Council reserves to enable an outline business case of the existing
leisure and community sites (the existing site) to be determined. |
|
7.
To authorise the Director of Services to agree the maintenance arrangements
for the land to be transferred to Amersham Town Council. |
|
8.
To authorise the Director of Services to agree the provision of replacement
outdoor leisure facilities to be managed and owned by Amersham Town Council
following the transfer of the section of King George V Playing Fields to be
developed to the District Council. |
|
9. That the Chiltern Life Centre is
built to high sustainability standards. |
|
10.
That the contractual arrangements to operate the leisure centres and
contractor responsible for developing the Chiltern Life Centre be appointed
simultaneously. |
Supporting documents: